Getting started with #ProjectOnline Part 5 #PS2013 #Office365 #Project #PPM #SharePointOnline #PM
|
I am a Project Server and SharePoint consultant but my main focus currently is around Project Server.
I have been working with Project Server for nearly five years since 2007 for a Microsoft Gold Certified Partner in the UK, I have also been awared with the Microsoft Community Contributor Award 2011. I am also a certified Prince2 Practitioner. This article has been cross posted from pwmather.wordpress.com (original article) |
In part 5 of the getting started series we will look at Enterprise Project Types (EPTs) and Project Detail Pages (PDPs). The last post, in case you missed it was looking at PWA Views:
Firstly we will look at PDPs and create a new PDP, we will then look at EPTs and create an EPT.
Project Detail Pages, known as PDPs are used use either display details or capture details for projects.There are several PDPs out of the box, lets look at creating a new one. As a PWA Admin navigate to PWA Settings and click Project Detail Pages under the Workflow and Project Details Pages heading:
Here you will see the PDPs that are included out of the box:
To create a new PDP click the Files tab > New Document > New Document:
Enter a name for the new PDP, choose the layout required and click Create:
You will then see a SharePoint web part page:
Click Add a Web Part and you will see the web part categories appear:
Scroll down to the Project Web App Category and you will see all of the Project Web App web parts. You can add any type of web part of these pages, it doesn’t have to be a Project Web App web part but for the purpose of this post I am going to add a Project Web App web part. The type of web part you add will depend on the purpose of the PDP, this example PDP is used for editing multiline project level custom fields so I will add the Basic Info web part. PDPs are the only place you can edit and view multiline project level fields in PWA. After selecting the required web part click Add and you will see the web part appear:
I have created two example multiline project level fields called “Project Status Summary” and “Project Actions”. These fields will be added to my example PDP. To add the fields, click the Edit Web Part option on the Basic Info web part:
Click the Modify button:
Add the fields that you want to see on the PDP, for the example I have added to the multiline custom fields I had created:
Click OK. Edit other web part properties as required, I have updated the title and the chrome then click Apply on the web part properties then click OK.
Click Stop Editing in the top left corner. Now click Edit Properties and enter a description:
The other properties can remain the same. The key property for PDPs is the Page Type, there are three options:
- New Project – this is used for creating a project
- Workflow Status – this is used to display the stage and status information
- Project – this is used for editing a project
Click Save. Now click the cog > PWA Settings:
Then click the Project Details Pages link and you will see the new PDP:
Now we have created a new PDP we need to be able to view this page, by default the users wont be able to use it or see it. This is where the Enterprise Project Types come into play.
Enterprise Project Types, known as EPTs are used as a container or wrapper if you like. The different project components are associated to the EPTs, for example any workflows, project plan templates, PDPs, project site templates. EPTs are used to create different types of projects, for example you might have a requirement for HR type projects and R&D projects, both of which have different requirements. HR projects might be required to capture different information for the project and project site compared to the R&D projects. R&D projects might require a project lifecycle workflow but the HR projects might not. All of this is possible using EPTs.
You get two EPTs out of the box, the SharePoint Task List and the Enterprise Project. The Enterprise Project EPT would be the default to use for full Project Online functionality. Lets look at creating a new EPT. As a PWA Admin navigate to PWA Settings and click Enterprise Project Types under the Workflow and Project Details Pages heading and you will see the table below:
You can see the two default EPTs. Click the New Enterprise Project Type button and you will see the new EPT form:
Enter a name, for this example we are going to create a Product Design EPT, so the name will be Product Design. Enter a description if required. Leave the other options as default and scroll down to the New Project/Project Detail Pages section and change the New Project Page to the Project Information PDP then add the other PDPs you wish to see for the type of project. For this example I have added the Schedule, Project Status Information and the Project Information PDPs. Project Status Information PDP was the PDP I created in the post:
Scroll down past the other settings until you get to the Image section, the others will be default. The Image setting allows you to set an image for the EPT, this can be seen when the user clicks the New button in the Project Center. For this example we will just use the default EPT image:
You have the option to change the order of the EPTs, for this example we will place this new EPT at the end. Scroll down to the Project Plan Template and Project Site Template sections:
This is where you can specify a plan template and a project site template. For now we are going to leave these as default because we do not have any plan templates in the environment or any custom project site templates. Click Save to create the new EPT. You will now see the new EPT:
That is it for the intro to EPTs until the next post. The next post in the series will look at project plan and project site templates, this will also touch on EPTs as we add our new templates to the Project Design EPT.
Getting started with #ProjectOnline Part 4 #PS2013 #Office365 #Project #PPM #SharePointOnline #PM
|
I am a Project Server and SharePoint consultant but my main focus currently is around Project Server.
I have been working with Project Server for nearly five years since 2007 for a Microsoft Gold Certified Partner in the UK, I have also been awared with the Microsoft Community Contributor Award 2011. I am also a certified Prince2 Practitioner. This article has been cross posted from pwmather.wordpress.com (original article) |
This is part 4 for the getting started with Project Online series. In the last post we looked at configuring the Enterprise Global:
In this post we will move back to PWA and continue with the configuration there. Next up are the PWA views, these are configured on the PWA Settings page. To access this page, click the cog menu and click PWA Settings:
Now click Manage Views under the Look and Feel heading:
You will see many preconfigured views here:
Above are the Project views, below are all of the view types that have preconfigured views:
As you can see there are quite a few different types of views in PWA, these are for different areas or functionality in Project Server. A summary for each view can be seen below:
|
View Type |
Description |
| Project | This type of view is used to view the tasks, assignments and resource details for a particular project. The views are found in the Project Detail Page, these are accessed after clicking the project from the Project Center. |
| Project Center | This type of view is used to view the project information in the Project Center. |
| Resource Assignments | This type of view is used to view information about specific resource assignments . These are accessed from the Resource Center in the resource assignments page. |
| Resource Center | This type of view is used to view resource information in the Resource Center. |
| My Work | This type of view is used by the team members to view and update their assignments. |
| Resource Plan | This type of view is used to build resource plans for projects. |
| Team Tasks | This type of view is used by team members to view tasks that their team is assigned to. |
| Team Builder | This type of view is used to build the team for a project. |
| Timesheet | This type of view is used by team members to complete their timesheets to report time against projects or admin time. |
| Portfolio Analyses | This type of view is used to view project proposals and review which best align to the organisations strategic goals. |
| Portfolio Analysis Project Selection | This type of view is used to approve the proposals as projects. |
For the purpose of this post we will create one Project view, one Project Center view and Resource Center view. Each view type has different settings and fields available, for example task level or assignment level fields are not available in a Project Center view. To create a new view we can either start with a blank view or copy an existing view, for the Project view we will copy the Task Summary view. To do this, select the Task Summary view:
The Copy View button is now enabled, click this button and a pop up will appear with a field to type the new view name, by default it will have “Copy of Tasks Summary”, update this with the name of the new view:
Click OK to create the new view, this new view will appear on the grid. Click the new view to load the edit view page:
Scroll down to the fields section and select a new field from the available fields, for the purpose of this post I am going to select the RAG Planned Work field that was created in post 2 and add this to the view.
Save the view. Now we will create a new Project Center view, click the New View button and select Project Center from the view type menu:
Type a name in the Name field and add a description if required. In the field section add the required fields, for the purpose of this post I will be adding the 3 custom project level fields created in post 2:
You have the option to set the field width and give the field a custom title / label.
Scroll down the the format view section and set the required options. For this example I have set the grouping format to Views, the group by to Programme and sort by to Project Name:
Now save the view. The third view we will create is a Resource Center view, click New View again and select Resource Center from the type menu and give the view a name:
Add in the required fields, in this example I will add some of the default fields plus the Employee Contract Type custom field created in post 2:
Scroll down to the Filter section and click the filter button, this will load a pop up for the custom filter:
Add the filter required, in this example it will be where the resources are full time:
Notice the filter is validate. Click OK and save the new view. That is it for the PWA views in this post but that should be enough to get you started. Next up we continue with other Project Online configuration to help you get the most out of your new environment.
How to hide fields for new items using InfoPath
A client had a fairly simple request to hide some fields when a new SharePoint list item is created but have these fields shown once the item has been created and people edit the form. The short version is that you can use the inbuilt ID field to see if an item is new or not. If the ID field is blank then it is a new form.
Here are the steps required so that you can hide fields when an item is being created. Make sure not to hide any required fields or the form cannot be saved.
These steps require InfoPath 2010 client to be installed
1. Navigate to the list
a. I have created a very simple list where users will ask a question. The goal is only to allow users to fill out the title field when an item is created
2. From the ribbon select the Customize Form option
b. If this option is missing then following feature is probably not activated
3. A form will now have opened in InfoPath 2010
4. Each field can be hidden manually or all of the fields you want to hide can be added to a new section and then you just hide the section.
a. Select the Section control and add to the bottom of the form
b. Copy or cut the required rows or fields from the table into the section. It will look similar to the following screen shot
5. Now we need to add a rule to the section to hide it.
a. Select the Manage Rules option from the ribbon
c. Highlight the section (Click on it)
e. From the Rules menu on the left hand side select New and then Formatting.
i. Change the name to be Hide Section
ii. Click on the None under condition and change it to the following
iv. Now select the Hide this control option
v. The whole rule should look like
6. Using the publish button in the very top left of InfoPath publish you changes back to the server.
a. You should receive an OK message once this is complete
7. Now navigate to the list and test to see if it has worked
Here is the new form
This is what the form looks like when an existing item is edited
This is just a very basic example. The overall style of the form can be changed using the formatting option within InfoPath.
Rule can also be applied directly to some fields so they do not have to be moved into a section if you do not want to. The attachment control must be added to a section as rules cannot be applied against this control directly.
via Buzz Blog http://bit.ly/LK0nvp
|
Paul is a an expert SharePoint and Project Server developer and is responsible for designing and implementing custom solutions on client systems using the latest SharePoint and .NET technologies.
Paul has extensive experience with SharePoint systems across all sizes of implementation, ranging from small to large farms and has an excellent understanding of all the elements of SharePoint. This article has been cross posted from paulbuzzblog.wordpress.com (original article) |
#ProjectServer #PS2013 access to Create Projects functionality #SP2013 #PM #Project #ProjectOnline
|
I am a Project Server and SharePoint consultant but my main focus currently is around Project Server.
I have been working with Project Server for nearly five years since 2007 for a Microsoft Gold Certified Partner in the UK, I have also been awared with the Microsoft Community Contributor Award 2011. I am also a certified Prince2 Practitioner. This article has been cross posted from pwmather.wordpress.com (original article) |
Just a quick post to detail the permissions required to be able to use the “Create Projects” button on a list in the PWA site collection. If you are not familiar with the button or functionality see the post below:
The permissions required for a user to be able to create a project from the SharePoint list in PWA when using the Project Server Permission mode are:
Global Permissions:
Manage Lists in Project Web App – this enables the button in the ribbon, without this permission the button remains greyed out / disabled even when you have an item selected in the list
New Project – this enables the user the see the form that pops up with the field mappings, without this the pop with display the message below:
Category:
Only included the Selected Projects + The User is the Project Owner or the User is the Status Manager on assignments within that Project
with Publish Project permission for that category, without the category and publish permission the create project button on the field mapping window will display the message below:
Getting started with #ProjectOnline Part 3 #PS2013 #Office365 #Project #PPM #SharePointOnline #PM
|
I am a Project Server and SharePoint consultant but my main focus currently is around Project Server.
I have been working with Project Server for nearly five years since 2007 for a Microsoft Gold Certified Partner in the UK, I have also been awared with the Microsoft Community Contributor Award 2011. I am also a certified Prince2 Practitioner. This article has been cross posted from pwmather.wordpress.com (original article) |
Part 3 of the “Getting started with Project Online” series looks at Project Professional 2013 Enterprise Global objects. Part 2 of the series looked at Project Online Enterprise Custom Fields:
Now that you have created your custom fields you need to make these visible to users. Views can be created for Project Web App (PWA) and Project Professional 2013. This post will look at the custom Project Professional 2013 Enterprise views and other custom Enterprise Global objects. These are stored in the Enterprise Global with the other default Enterprise Global objects. You do get a lot of views, groups and filters etc. with Project Professional 2013 that are stored in the local global file, these are known as local objects (views, filters etc.). The Enterprise Global is a file that is used to control what objects are standardised across the organisation for Project Professional when connecting to Project Online / Project Server 2013. When Project Professional is connected to Project Online / Project Server, the Enterprise Global and the local global file merge so that both the Enterprise objects and local default objects are available. The type of objects are views, tables, groups and filters. The next steps will create custom objects in the Enterprise Global for your environment.
Launch Project Professional 2013 and connect to the PWA instance. If you haven’t connected Project Professional to PWA before see the steps below:
- Launch Project Professional 2013
- Click File > Info > Manage Accounts
- Click Add
- Enter an account name – this is your reference
- Enter the Project Server PWA URL, it will be something like https://<tenantname>http://.sharepoint.com/sites/PWA
- Set as default account
- Click OK
- Check the box to choose an account
- Click OK then close and re-launch Project
- Now you will be prompted to choose an account
- Select the account that you just created
- Click OK
If you haven’t connected before you might be prompted for credentials, enter details for an account that has admin access to PWA. Your Project Professional client will now be connected to your Project Online PWA instance.
Once Project Professional is connected we can start the configuration of the Enterprise Global file. Close the blank Project 1 file and Click File > Info > Organiser > Open Enterprise Global
It will look like a blank project but notice the title “Checked-out Enterprise Global”:
We are now ready to add the custom enterprise objects. For the purpose of this post we will create 1 custom view that includes some of the default Project fields but also our custom RAG Planned Work field, we will also create a custom filter. Firstly we will look at creating the custom Enterprise Global view. Views are based on tables, so firstly we need to create a table, this table defines the fields and the layout in the view. In Project Professional, click the View tab then the Tables > More Tables:
Click New:
Enter a Name, I would recommend that you prefix all of the custom Enterprise Global objects with a set of characters so that you know they are custom. When you have many custom objects in the Enterprise Global you will be glad you did this! Then add the fields required, set the width and add a custom title plus any other settings you would need, see example below:
Click OK then Close. Now create the view, click Other Views > More Views on the View Tab:
Click New:
Select Single view and click OK. Single view will create just one view, a combination view will give you a split view. For example, for a combination view you might have the Gantt view at the top (Primary) and the Task Usage at the bottom (Details). For this example we will create a single view:
Give the view a name, remember the prefix tip, and select the other options as displayed below:
The Table is the name of the table we created in the previous step. Click OK then Close. That’s the view created, now lets create the custom enterprise filter. Click the Filter drop down and select More Filters:
Click New:
Enter a name then set up the filter, in this example I want the filter to display all tasks where the RAG Planned Work field has a value of “Planned Work Greater Than Baseline”:
This value is from the formula from the RAG Planned Work field.
Click Save then Close.
Now save the Checked-out Enterprise Global file, File Save. Close and check in the Enterprise Global file. Exit Project Professional then re-launch it and connect to the account we created in the first steps so that you are connected to the Project Online PWA instance. This process is required so that Project loads with the new Enterprise Global file. You will now see that the new view and filter are available:
View selected:
Notice only the fields we defined in the table are visible. The custom filter is also available:
Selecting this filter on a project will only show tasks that have more planned work than the baseline value, no filter:
Selecting the custom filter just created:
That covers the intro to custom Enterprise Global objects, in the next post we will look at further configuration entities in PWA.
Getting started with #ProjectOnline Part 2 #PS2013 #Office365 #Project #PPM #SharePointOnline #PM
|
I am a Project Server and SharePoint consultant but my main focus currently is around Project Server.
I have been working with Project Server for nearly five years since 2007 for a Microsoft Gold Certified Partner in the UK, I have also been awared with the Microsoft Community Contributor Award 2011. I am also a certified Prince2 Practitioner. This article has been cross posted from pwmather.wordpress.com (original article) |
This is part 2 of the “Getting Started with Project Online” series. If you didn’t see part one see the link below:
In summary this post covered creating the PWA site collection, we went from nothing to having a fully functional Project Online environment in around 45 minutes!
In this post we will look at what to do next now that we have a blank Project Online PWA site collection.
Before we move to the PWA site collection, there is a decision that needs to be made regarding the permission mode. With Project Server 2013 and Project Online there are two permission modes available. Either the SharePoint Permission mode or the Project Permission mode. By default the PWA site collection is provisioned using the SharePoint Permission mode. If you are just starting out with Project Online and you are not familiar with the classic Project Permission mode I would recommend you stick with the SharePoint Permission mode as this will simplify the configuration and administration. We wont go into details on the differences but to help you decide, see the following TechNet link:
Should you wish to change the permission mode if the SharePoint Permission mode doesn’t meet your organisations access security requirements, navigate to the SharePoint Admin Center. If you don’t know the URL the easiest way to access this is from the PWA site, in the top corner you will see an Admin drop down menu when logged in with an Office 365 tenant admin account:
Click SharePoint, that will take you to the SharePoint Admin Center:
From this page, select the PWA site collection (check box next to the PWA site collection) then click the Settings link under the Project Web App menu as displayed below:
This will load the Settings page for the Project Web App site:
As you can see, the SharePoint Permission Mode is already set. For the purpose of these posts, we will leave this set but this is where you can switch your PWA site collection to use the Project Permission mode. You can switch permission modes at any time but bear in mind the settings will be reset so you will need to reconfigure the permissions / add users to the PWA site collection again – best to decide the permission mode from day one to avoid a lot of work on a live system! Also another key piece of information on this page is the Project Database Usage, you get 10GB for Project Online so worth monitoring / checking this.
Now we have covered the permission mode, we can move the the PWA site collection and start the configuration. Load the PWA site collection with the PWA Administrator account that you specified on the site creation and you will see the following site as we saw in the previous post:
The first part of the configuration we need to consider is the PWA custom fields as the other configuration elements require these to be in place so lets find these. To access the PWA custom fields, navigate to the PWA Settings page. Click the settings cog in the top left corner:
Click PWA Settings and you will see the following page:
This page is where you configure all of the PWA settings. So we are looking for custom fields, under Enterprise Data you will see “Enterprise Custom Fields and Lookup Tables”, click that link and you will see the custom field page:
You will notice there are custom fields and lookup tables already in place, these are the default fields that are created with the Project Online / Project Server PWA instance. This doesn’t include the intrinsic fields, for a reference of these fields see the following link:
One thing I will point out at this stage as it is the first time we have seen any locale specific data (Last Updated column), you will notice this has the US date format. To change this to the correct locale for your users, click the settings cog again then Site Settings:
Now click Regional Settings under the Site Administration heading:
On this page select the correct locale and other region specific settings:
Then Click OK and navigate back the PWA Settings page from the site cog menu then click the “Enterprise Custom Fields and Lookup Tables” link and notice the date format is now correct for the UK:
Before we look at creating custom fields lets have an overview of the types of fields available. We can create Project, Resource and Task level fields that are one of the following types of field: Cost, Date, Duration, Flag, Number or Text. You also have Lookup Tables that can be associated with the text based custom fields if required. Customs fields based on lookup tables are used to “tag” the data with a certain value or values, this can then used for grouping, filtering and sorting in views or reports. Other fields can be used for grouping, sorting and filtering but generally the fields based on lookup tables or formulas are used as you know the possible values that are available. You can also create your own calculated fields by choosing the Formula attribute. Also you have other attributes that can be set such as the rollup for summary rows and roll down for assignment rows, this settings is only available for Resource or Task fields. There is also the option to either show the value of the field or display a graphical icon. Graphical icons would only really be set on fields that are either based on a lookup table or a formula as you know all the possible values.
Full details on custom fields can be found here:
We will now walkthrough creating a few custom fields. At this stage I would hold off creating these on your PWA environment as now is a good time to sit down with your peers and discuss / review the fields your organisation needs. The best way to start is to think about what do you want out of the system, what data do you want to capture, what data do you want to report on etc. We will continue here though and create a couple of Project, Resource and Task fields.
We will create the project level fields first, from the custom fields page click the New Field button:
The new field page will look like this:
This field is going to be a “Project Code” field to sort a project code against each of our projects. I have set the following settings:
Name: Project Code
Description: Enter the project code
Entity and Type: Entity: Project Type: Text
Custom Attributes: Single line of text
Department: NA – left empty
Behaviour: Require that this field has information: Yes | Other settings default
Before we move on I just want to mention a couple of the field attributes, Department and Behaviour. The department field is used to departmentalise the configuration and data in PWA. We aren’t going to use this functionality here but it can be very useful if you want to change what custom fields are visible to users / projects as it might be that not all fields are applicable to all users / projects. There are a few blogs out there that cover this topic quite well if you want to look at using this feature. The other attribute is Behaviour, a field can be controlled via a workflow as part of the project lifecycle, we aren’t setting up a project lifecycle workflow so will leave this unchecked.
Once the settings have been completed, click Save on the new custom field page and you will be taken back to the custom field admin page and see your new field:
The next project level field is going to be a text field based on a lookup table, the field is going to be called Programme. When you want to use a lookup table on a field the lookup table needs to be created first. Click the “New Lookup Table” button and the following page will load:
A lookup table as a few attributes, Name, Type, Code Mask and the Lookup Table. Choose the type of lookup table, the options are Cost, Date, Duration, Number and Text. The Code Mask is only applicable for text based lookup tables as these can be hierarchical with different levels, the code mask set the levels available and the separator. For this example I am using a text based lookup table with 2 levels set on the code mask then populated the table with my Programme values:
Use the toolbar functions on the lookup table to outdent, indent, delete and insert rows etc. Once you are happy with the lookup table click save. At this point the lookup table is validated against the code mask, in this example all is fine and saves ok. If you see this error on save, the code mask is not correct for the levels you need or you have enter to many characters as 255 is the limit for one value (row):
“The lookup table could not be saved due to the following reason(s): One or more code values in the lookup table either do not match the mask defined for the code or contain more than 255 characters.”
Now that we have a lookup table we can create the associated project level custom field. Click the “New Field” button. Enter the field name, leave this as a Project Text field. On the custom attributes, check the Lookup Table option:
Change the lookup table to the Programme lookup table we just created, in this example the other options for the lookup table will be left as default. We will set this field to display the data rather than an indicator and leave the behaviour attributes as default so this field is not required. Click Save and you will see the new field on the custom field table:
The final project level field we will create is a Project Status field, this will also use a lookup table. Create a new text based lookup table called “RAG Status” with 3 values Red, Amber and Green. Then create a new field called “Project Status”, in the description state this is a manually set RAG field, set the Lookup table attribute to use the “RAG Status” lookup table that was just created:
Scroll down and set the field to use graphical indicators and you will see another table appear:
Populate the table as follows:
The important part is the Test and the Value, the value must match the value in the associated lookup table otherwise the image will never be displayed. I have also set the data value to be displayed in a tooltip. Once the settings are complete, click Save. We now have 3 custom project level fields.
Next we will look at creating a Task level formula based field called RAG Planned Work, click the New Field button, set the name and select Task then Text. Check the Formula custom attribute then type the required calculation. For this example the nested if statement below will be used:
IIf([Work] = 0, "No Planned Work", IIf([Baseline Work] = 0, "No Baseline Work", IIf([Work] <= [Baseline Work], "Work Within Baseline", "Planned Work Greater Than Baseline")))
If you are new to Project formulas, notice the IIF, it is an immediate if.
This can be seen here:
For this example we will set the summary row calculation to use the formula but the assignment row calculation will be set to none. We will also set this to use graphical indicators as follows:
The values for the graphical indicators match the possible values in the formula. Once completed click Save. At this point the formula will be validated and not let you save the page if there are errors.
The final field we will create is a resource level field called Employee Contract Type, this will use a lookup table. As before, first create a text based lookup table called Contract Type with the contract values. This will include values like Full Time, Part Time, Contractor and 3rd Party as seen below:
Save the new lookup table and click the “New Field” button and set the name, then choose Resource from the Entity menu and Text from the Type menu. On the custom attributes menu select Lookup Table and choose the Contract Type lookup table:
Set the field to be required in the Behaviour section and click Save. We now have our example enterprise custom fields and lookup tables created:
Hopefully now you are comfortable with the options available to create the remaining fields your organisation requires. That brings us to the end of the first part of the configuration, in the next part we will continue with the other elements of the configuration.
Getting started with #ProjectOnline Part 1 #PS2013 #Office365 #Project #PPM #SharePointOnline #PM
|
I am a Project Server and SharePoint consultant but my main focus currently is around Project Server.
I have been working with Project Server for nearly five years since 2007 for a Microsoft Gold Certified Partner in the UK, I have also been awared with the Microsoft Community Contributor Award 2011. I am also a certified Prince2 Practitioner. This article has been cross posted from pwmather.wordpress.com (original article) |
This post is the first post from a series of posts I am going to write based on Project Online. It is very simple to get a Project Online Office 365 tenant but once the PWA site collection is there, what next? Where do you start? How do you get the most out of it? This series of posts will guide you through these steps so that hopefully you get the most out of Project Online.
Firstly I will go through creating the PWA site collection, for this you will need tenant admin access as this is created from the SharePoint Admin site on the Office 365 Admin center.
From the Office 365 Admin site below:
Click Admin > SharePoint:
On this page you can manage all the SharePoint related functionality:
As you can see, there is already one PWA site collection on this tenant, you can have up to 3 per tenant. To create a new PWA site collection click New > Private Site Collection with Project Web App
This will load a form, the completed form can be seen below:
Click OK. You will now see the new PWA site collection appear but with a spinning circle that states “The site collection is being created.”
After approximately 10 to 15 minutes the PWA site collection will be ready and accessible, notice the NEW text in green:
Clicking the new PWA site link will load the site collection properties:
Click the Site Address and the PWA site will load:
There it is, in a handful of steps you now have a fully functioning Project Online PWA site collection.
Next up we will begin configuring and customising the Project Online site collection.
#SSRS native report render issue in #SharePoint #SP2013 with #IE 9 or later #PS2013 #BI #SQL
|
I am a Project Server and SharePoint consultant but my main focus currently is around Project Server.
I have been working with Project Server for nearly five years since 2007 for a Microsoft Gold Certified Partner in the UK, I have also been awared with the Microsoft Community Contributor Award 2011. I am also a certified Prince2 Practitioner. This article has been cross posted from pwmather.wordpress.com (original article) |
This post covers an the details around an issue I came across the other day and I wanted to make you aware to help in your deployments / system design. The issue is with displaying SSRS Native mode reports on a SharePoint 2013 page using a page viewer web part when using IE 9 or later. Our preference and recommendation is to usually use SSRS Integrated mode but on occasions some of our clients use SSRS Native mode. This issue doesn’t exist for SSRS Integrated mode.
The is that the SSRS reports are not displayed correctly on the page, they are truncated:
Other standards-compliant browsers are ok, Chrome is:
IE 8 also works fine.
The page viewer web part with SSRS Native reports worked fine in SharePoint 2010 in any browser.
I have tested with the SSRS Report viewer web part (the 2008 R2 version as the SQL 2012 version doesn’t deploy to SharePoint 2013) from the RSWebParts.cab file, this has the same issue.
One of our devs had a quick look at this and it stated it was because the web part uses a table that is 3 cells wide. 2 of the cells are related to the document map while the 3rd contains the report itself. The document map cells are hidden by default.
In older versions of IE, a hidden cell in a table counted towards with width of the table, this was against the standard. Now with more standards compliant browsers, hidden cells do not count towards the width of the table.
This means that the report cell is the only cell defined for the row, so the browser forces it into the left most cell space. The end result of this is the SSRS report is truncated to the right as that is the limit of the size of that column.
So the answer going forward if your client wants to embed SSRS reports in SharePoint 2013 pages and they use IE, recommend (and use) SSRS 2012 Integrated mode.
Updating database collation
Had some fun trying to update a database collation. I didn’t have to worry about the data i just needed to the collation changed so that some cross database scripts would still function in order to carry out some testing.
Here is a nice little script I found that will generate scripts to change the collation on the required columns. Some of it fails if primary keys or indexes are against the columns but this will do 90%.
SELECT
CAST(o.table_name + ‘ -> ‘ + c.name AS VARCHAR(60))
, ‘ALTER TABLE ‘ + o.table_name +
‘ ALTER COLUMN [‘ + c.name + ‘] ‘ +
UPPER(t.name) + ‘(‘ +
CASE
WHEN t.name IN (‘nchar’, ‘nvarchar’) AND c.max_length != -1 THEN CAST(c.max_length / 2 AS NVARCHAR(10))
WHEN t.name IN (‘nchar’, ‘nvarchar’) AND c.max_length = -1 THEN ‘MAX’
ELSE CAST(c.max_length AS NVARCHAR(10))
END + ‘) COLLATE ‘ + @collate +
CASE WHEN c.is_nullable = 1
THEN ‘ NULL’
ELSE ‘ NOT NULL’
END
FROM sys.columns c WITH (NOWAIT)
JOIN (
SELECT
table_name = ‘[‘ + s.name + ‘].[‘ + o.name + ‘]‘
, o.[object_id]
FROM sys.objects o WITH (NOWAIT)
JOIN sys.schemas s WITH (NOWAIT) ON o.[schema_id] = s.[schema_id]
WHERE o.[type] = ‘U’
) o ON c.[object_id] = o.[object_id]
JOIN sys.types t WITH (NOWAIT) ON c.system_type_id = t.system_type_id AND c.user_type_id = t.user_type_id
WHERE t.name IN (‘char’, ‘varchar’, ‘text’, ‘nvarchar’, ‘ntext’, ‘nchar’)
–AND c.collation_name != @collate
ORDER BY
o.table_name
, c.column_id
via Buzz Blog http://paulbuzzblog.wordpress.com/2014/01/10/updating-database-collation/
|
Paul is a an expert SharePoint and Project Server developer and is responsible for designing and implementing custom solutions on client systems using the latest SharePoint and .NET technologies.
Paul has extensive experience with SharePoint systems across all sizes of implementation, ranging from small to large farms and has an excellent understanding of all the elements of SharePoint. This article has been cross posted from paulbuzzblog.wordpress.com (original article) |
Changing the format of date parameters on SSRS 2012
Had an issue today where the date parameters were being forced into US data format and not using any of the regional settings from the OS or SharePoint.
This has apparently been fixed in SQL 2012 SP1 CU5 update but i have not confirmed this.
Has a workaround that required you to add a culture into the RSViewerPage.aspx located in
C:\Program Files\Common Files\Microsoft Shared\Web Server Extensions\14\TEMPLATE\LAYOUTS\ReportServer
or
C:\Program Files\Common Files\Microsoft Shared\Web Server Extensions\15\TEMPLATE\LAYOUTS\ReportServer
in SharePoint 2013
You need to add UICulture="en-GB"
to the end of
<%@ Page language="C#" Codebehind="RSViewerPage.aspx.cs" AutoEventWireup="false" Inherits="Microsoft.ReportingServices.SharePoint.UI.RSViewerPage,Microsoft.ReportingServices.SharePoint.UI.ServerPages,Version=11.0.0.0,Culture=neutral,PublicKeyToken=89845dcd8080cc91" %>
The full string looks like
<%@ Page language="C#" Codebehind="RSViewerPage.aspx.cs" AutoEventWireup="false" Inherits="Microsoft.ReportingServices.SharePoint.UI.RSViewerPage,Microsoft.ReportingServices.SharePoint.UI.ServerPages,Version=11.0.0.0,Culture=neutral,PublicKeyToken=89845dcd8080cc91" UICulture="en-GB"%>
If you are using Windows 2012 i had to save the updated file to a different location and then copy the file in and gain the correct permissions.
via Buzz Blog http://paulbuzzblog.wordpress.com/2014/01/10/changing-the-format-of-date-parameters-on-ssrs-2012/
|
Paul is a an expert SharePoint and Project Server developer and is responsible for designing and implementing custom solutions on client systems using the latest SharePoint and .NET technologies.
Paul has extensive experience with SharePoint systems across all sizes of implementation, ranging from small to large farms and has an excellent understanding of all the elements of SharePoint. This article has been cross posted from paulbuzzblog.wordpress.com (original article) |









You must be logged in to post a comment.