Home > CPS Cross Post, EPM, Project Server, Project Server 2010, PS2010 > Hiding tasks from the Gantt Chart

Hiding tasks from the Gantt Chart

Have you ever wanted to hide tasks from the Gantt Chart? The following technique is useful for tidying up a schedule – for example, if you want to show only pertinent Gantt information for a presentation, or take a screenshot of a plan for a client that contains some internal tasks.

To hide individual bars in the Gantt display, simply insert the “Hide Bar” field and set it to “Yes” for the requisite tasks:

image

After hiding:

image

You’ll notice that all incoming dependencies for the hidden bar are also hidden, so take care when looking at your predecessor/successor logic!

Lester

Advertisement
  1. No comments yet.
  1. January 21, 2013 at 09:20

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: