#ProjectServer / #ProjectOnline error opening Enterprise Resource Pool #MSProject #Office365 #PPM
|
I am a Project Server and SharePoint consultant but my main focus currently is around Project Server.
I have been working with Project Server for nearly five years since 2007 for a Microsoft Gold Certified Partner in the UK, I have also been awared with the Microsoft Community Contributor Award 2011. I am also a certified Prince2 Practitioner. This article has been cross posted from pwmather.wordpress.com (original article) |
A quick post to highlight an issue and workaround for opening the Enterprise Resource Pool in Project Pro using the Open button on the Resources tab in the Resource Center:
If you try and click the Open button with no resources selected in the grid you will get the error below:
“This action couldn’t be performed because Office doesn’t recognize the command it was given” :
Select at least one resource in the grid then this command will work fine.